Project Profile: Office to Lab Conversion at 9900 Belward Campus Drive, Rockville, Maryland.

Budget (Phase 1): $3,400,000

Project Size (Phase 1): 15,000 sq ft

Key Elements: 45,000 sq ft office building conversion to a lab ready facility. The first phase included the buildout of two 7,000 sq ft spec lab/offices

Third Floor Plan

9900 Belward Campus Drive Third Floor PLan

Lab Build Out

9900 Belward Campus Dr Lab 9900 Belward Campus Dr Lab 9900 Belward Campus Dr Lab
9900 Belward Campus Drive, Lab Conversion 9900 Belward Campus Drive, Lab Conversion